Naval Today
  • Vessels
  • Equipment & Technology
  • Operations
  • Capital Investments
  • Authorities
  • More news
JobsNewsletter
Naval Today logo

Your trusted source for naval and maritime news, part of the Navingo network.

Topics
  • Equipment & technology
  • Industry
  • Vessels
  • Operations
  • Training & Education
Network
  • NavalToday
  • Dredging Today
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Submarines›US Navy’s Los Angeles-class submarine returns to fleet
Submarines

April 13, 2017 · about 9 years ago

US Navy’s Los Angeles-class submarine returns to fleet

U.S. Navy’s Los Angeles-class submarine USS Providence (SSN 719) returned to the fleet on April 7 after completing a maintenance period that will allow her to complete her remaining scheduled deployments before being retired. The submarine started her pre-inactivation restricted availability (PIRA)

1 minutes read
  • LinkedIn
  • X
  • Email

U.S. Navy’s Los Angeles-class submarine USS Providence (SSN 719) returned to the fleet on April 7 after completing a maintenance period that will allow her to complete her remaining scheduled deployments before being retired.

The submarine started her pre-inactivation restricted availability (PIRA) period at Portsmouth Naval Shipyard on December 4, 2015, and returned to fleet 23 days ahead of schedule and on budget, according to the U.S. Navy.

“As a team, the shipyard with the captain and crew of Providence, focused on the positive plan forward,” said project superintendent, Mark Ayotte. “Together we reached our goal of getting the warfighter underway to do what they do best for the Navy and our country.”

The project team and crew thrived in an environment that promotes increased levels of collaboration, innovation and high velocity learning. Their teamwork coupled with the shipyard’s collective commitment to excellence ensured non-stop execution of work.

Providence’s PIRA was approximately 200,000 mandays of work scheduled for a 15.7 month time frame. The project team and crew completed the complex work package more than three weeks ahead of schedule.

USS providence is a 32 year old boat and, like the rest of the submarines in her class with a nominal service life of 33 years, is awaiting retirement.

Providence was built by General Dynamics Electric Boat and launched in August 1984. She was commissioned into the navy on July 27, 1985.

Reach the Naval Today industry in one go!

Naval Today is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Naval Today on:

Filed under

SubmarinesVesselsAuthoritiesDefense Strategies

Daily Naval, Defence and Maritime News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Lockheed Martin lands up to $1.2b for missile targeting moving ships
  2. 2Japan’s new high-speed landing craft hits the water
  3. 3UK's uncrewed submarine fires torpedo in historic AUKUS trial
  4. 4L3Harris gets $139M for US Navy submarine masts

Daily Naval, Defence and Maritime News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free