Fincantieri: Keel laid for Italian Coast Guard’s patrol vessel

Fincantieri and Cantiere Navale Vittoria have marked the laying of the keel of the multi-purpose offshore unit (UAM) destined for the Italian Coast Guard.

Fincantieri

As informed, the ceremony took place at the company’s yard in the Veneto region on 31 March. This symbolically and officially marks the beginning of the most significant part of the construction phase of the boat.

The design and construction of the “green” unit, worth around 80 million euros (including integrated logistic support activities and temporary service), was entrusted in 2021 by the General Command of the Port Authorities – Coast Guard to the temporary grouping of companies (RTI) formed by Fincantieri and Cantiere Navale Vittoria.

The UAM, with an overall length of 85 meters, is designed to fulfil the various missions entrusted to the Coast Guard, from sea rescue to navigation safety, from the protection of the marine environment to that of fish resources.

It will be used as a headquarters of operational command for the management of the various civil protection devices in intervention missions in response to severe disasters and calamities. It will be built entirely at the Veneto shipyard, with delivery scheduled for the end of April 2025.

The unit that will increase and enhance the operational capabilities of the Italian Coast Guard will be employed in long-range offshore operations (with a logistic autonomy of at least 20 days, more significant than 4,800 miles), in which it will be able to take on, thanks to and to the advanced communication and discovery systems present on board, also the role of command and control for the coordination of aeronautical means in the areas of operation.

The order and construction of the multi-purpose offshore vessel provide a five-year temporary support service and the option to build two additional ships.

With a total length of about 85 meters, the UAM will be characterized by high manoeuvrability, guaranteed by an electric propulsion system of the azimuth type powered by an electric power plant and by two bow thrusters bows for dynamic positioning that ensures the environmental sustainability of the vessel.

The presence of a large working deck with offshore cranes and a loading ramp for wheeled vehicles, together with the flight deck for landing and take-off of helicopters, dedicated rescue zones with relatively rigid keel inflatable boats (Rigid Hull Inflatable Boat), the anti-pollution systems (rec-oil), the hospital area and other equipment, favour the high versatility and the necessary multi-role capacity of the naval unit.

“The ship that is starting to take shape today, in concert with the partners of the Vittoria Shipyard, embodies many aspects that characterize our Group. The unit inherits the successful experience of constructing the Dattilo and Diciotti patrol boats, again for the Coast Guard… Furthermore, the philosophy behind the project is based on maximum operational versatility, another strong connotation of Fincantieri products,” Pierroberto Folgiero, Chief Executive Officer of Fincantieri, commented.